Acro Software Release Process Checklist
=======================================

***************************** PLAN ****************************** 

1. Release requested by
   ___ project manager
   ___ customer(s)
   ___ other: __________________________________________________

2. Release motivated by
   ___ new features
   ___ bug fixes
   ___ other: __________________________________________________

3. Release number:

   Acro:                ___
   Packages:
     APPSPACK           ___
     COLIN              ___
     Coliny             ___
     GNLP               ___
     OPT++              ___
     ParPCX             ___
     PEBBL              ___
     PICO               ___
     TMF                ___
     UTILIB             ___

4. Subversion revision number: __________________

5. ___ Identify customer(s): ___________________________________

6. ___ Identify or stakeholder(s): _____________________________

7. Dates:

   __________ release components checklist completed, checked in

   __________ release test plan identified, checked in

   __________ submit copyright paperwork

   __________ third party issues identified, checked in

   __________ individual project release checklists, checked in

   __________ configure/install and setup script working

   __________ testing complete

   __________ documentation complete

   __________ customer satisfaction plan created, checked in

   __________ release

9. Release to:
   ___ internal
   ___ external
   ___ specific customer: ______________________________________

10. Release Products
   ___ Source distributions
	External distributions:
	Internal distributions:
   ___ Executables
	External distributions:
	Internal distributions:
   ___ Documentation

11. Release formats (check all that apply):
   ___ zip file
   ___ CD
   ___ other: __________________________________________________

*****************************  DO ****************************** 
Initials
  |
  V

 ___ Communicate release plan to developers, in particular the
      dates and components identified in the release components checklist.

 ___ Communicate third party package requirements to third
         party contacts if necessary.

 ___ Do necessary copyright negotiations for packages

 ___ Update copyright information for third party packages

 ___ Create and check in customer satisfaction plan [customerSatisfaction.txt]

 ___ Create a preliminary release package.

 ___ Complete release plan preparation checklist [releasePreparation.txt]

 ___ Resolve build and test failures.

 ___ Create stable branch

 ___ Test code in stable branch and resolve issues.

***************************** CHECK **************************** 

 ___ Verify that all bugs, features and documentation identified in
      the PLAN have been resolved.

 ___ Verify that all necessary Release Process Checklists and
      required attachments have been completed.

***************************** ACT **************************** 

 ___ Create the release branch in the releases/{major}.{minor}.{revision}
     directory.

 ___ Update the distribution information in the
     dist/{major}.{minor}.{revision} directory
     ___ Test results
     ___ Release documentation
     ___ Release tarball

 ___ Certify release (project leader), date: ___________________

 ___ Deliver and announce release, date: _______________________

 ___ Update or improve release process if appropriate

 ___ Initiate plan for customer satisfaction, date: ____________